[VIEWED 20083
TIMES]
|
SAVE! for ease of future access.
|
|
|
|
shirish
Please log in to subscribe to shirish's postings.
Posted on 01-24-08 9:21
PM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
One of the main tussle between the late King Birendra and Indian Prime Minister Rajiv Gandhi were related to the water projects in Nepal.
India demanded that Indian companies given the first priority to any hydro and electricity related projects in Nepal but the then Govt refused to do so. Now after the LOKTANTRA, India holds keys on every political party to implement its interest and do as it wishes.
It is believed that in a decade, India will face severe water and power crisis/shortage and one of the ways to solve problem are utilization of Nepalese land and supply water and electricity to India.
Don't believe me....Keep watching !!
GMR lands 300 MW Upper Karnali
BY BIKASH SANGRAULA
KATHMANDU, Jan 25 - After five successive days of negotiations, the government decided late Thursday to award the 300 MW Upper Karnali project to India's GMR Energy Ltd.
The Ministry of Water Resources (MoWR) signed a Memorandum of Understanding (MoU) with a GMR team led by its Senior Vice President Avinash Shah Thursday evening, according to Anup Kumar Upadhyay, joint secretary at MoWR.
The decision was taken after GMR agreed to increase its free energy offer to Nepal from 7.5 percent to 12 percent (36 MW), said Upadhyay, who participated in the negotiations.
However, GMR's free equity offer has been dropped from 33 percent to 27 percent to compensate for the increase in the free energy component. GMR will also pay export tax and royalties to Nepal according to existing legal provisions, said Upadhyay.
"We signed an MoU incorporating these agreements," said Upadhyaya, who is a member of the team formed by the cabinet on December 30 to renegotiate the Upper Karnali and 402 MW Arun III projects with prospective developers.
The cabinet had directed the team to renegotiate the projects, with free energy as the highest priority for Nepal. The cabinet set 12 percent free energy from the Upper Karnali and 21.9 percent (88 MW) free energy from the 402 MW Arun III as base benefits for Nepal.
The cabinet had also directed the team to start negotiations with developers in the order of the ranking prepared last year by a taskforce led by former secretary Bhanu Prasad Acharya.
GMR was ranked as the company with the best proposals for both projects from among the 14 companies interested in Upper Karnali and nine companies interest in Arun III. Since GMR is getting the Upper Karnali, the team will now negotiate Arun III with the second ranked developer, India's Sutlej Jal Vidhyut Nigam. The cabinet had also directed the team to award only one project to one developer.
"We have invited Sutlej for negotiations on February 3," Upadhyay said.
GMR will have to pay the government Rs 100,000 per MW for project survey, and Rs 500,000 per MW in bank deposit before starting project construction.
Upper Karnali as well as Arun III are being developed to export power to India.
Though the Acharya taskforce had recommended that both projects be awarded to GMR, parliament's Natural Resources and Means Committee later directed the government to review the recommendation making free energy as the topmost priority.
GMR has set a target of 2.5 years for preparatory work on the project, and 4.5 years for construction.
Last edited: 24-Jan-08 10:06 PM
|
|
|
|
max n duku
Please log in to subscribe to max n duku's postings.
Posted on 01-25-08 10:12
AM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
guys i think the rat problem is killing our society. we need to kill the problem first. no matter the cat is white or black...
|
|
|
Sheetalb
Please log in to subscribe to Sheetalb's postings.
Posted on 01-25-08 10:49
AM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
I think the most important things is INDIA is our only customer to export Hydropower and it being a country full of smart people will try to take advantage of the situaiton of Nepali politicians.
I consider it a good move that Nepali government considered but i wishes like others pointed out that Nepali people did good homework before signing the document or even preparting MOU. I believe there is a saying among Indian politicians and diplomats that Nepalis (politicians) are not only Landloced but they are Mindlocked and hence they can always take advantage of us.
I wish our government make special department of water specialists to negotiate rather than making it a political agenda.
|
|
|
mohanB
Please log in to subscribe to mohanB's postings.
Posted on 01-25-08 11:49
AM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
The Government should make law that everybody has to invest certain percent on small scale hydropower projects. The smaller ones should be just enough for Nepal's consumption. We also need our own skilled engineers. Students should be encouraged to study hydro engineering than computer science.
|
|
|
Captain Haddock
Please log in to subscribe to Captain Haddock's postings.
Posted on 01-25-08 11:51
AM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
When it comes to hydro power we are between the devil and the deep-blue see. I agree with the point above about trade diversification - a very sensible strategy no doubt -but I am curious to know who the other bidders were, if any, besides the two finalists. As for the share of power and proceeds, I don't have enough information to judge how fair this is, but private-public sector cooperation in the power sector is in our future and the future has arrived (it actually did with Bhote Koshi and others I guess)
|
|
|
spreadlove
Please log in to subscribe to spreadlove's postings.
Posted on 01-25-08 12:06
PM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
My view
I see no harm Indian companies getting to build the hydro power plans in nepal.
I see harm in Nepalese who love to provoke anti-indian attitude without analysis. Its not indains who we are to be scared of, its of our own people who surrender because internally they realize that they are ignorant when it comes to debating with indian talence.The fact that we have potential and that we can do things on our own subsides and stand up for aimless ego trip and enjoy bickering India. See where india has reached today. the personalities of our leaders have been shadowed by indian leaders. Besides if a small creek runs parallel to an ocean the entire region is referred to as ocean, the creek becomes unnoticable. I thing most of the nepalese are suffering from that lack of attention phenomena when giant india is constatly noticed. Sheer jealousy. A lousy one. Lets learn something folks!!!!!
Instead of bickering lets reap benefits from the Indians. We have have to loose some but on a long run if handled properly we will rise high.
-sp...
|
|
|
presidentofnepal2035
Please log in to subscribe to presidentofnepal2035's postings.
Posted on 01-25-08 1:00
PM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
When will we know the importance of stable economy in Nepal than useless exaggerated sense of self importance and blabbering of hallow nationalism?
Bhutan is very much similar to Nepal in terms of geology. Bhutan was poorer than Nepal a decade ago. Now Bhutan is richer than Nepal and very less percentage of Bhutanese are under poverty, thanks to booming hydro power industry.
The fact is, it is not Indians who are taking advantage on us, rather it is us, Nepalese, who don’t know how to deal with big neighbors. We love to hate India because we think it is our moral right to hate them. And hating India make us think that we are pure nationalist.
|
|
|
CopiCat
Please log in to subscribe to CopiCat's postings.
Posted on 01-25-08 5:06
PM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
GP
No one is in America and abraod because he will die hungry in Nepal. I know many a fren who had decent job and good financial standing back in Nepal are in America, Australia, UK, Japan, etc. Even if we go back to Nepal now, we can live at least a moderate life (may not be the same as we are living abroad). No doctor will remain idle if they really go back to Nepal. Most of the engineers will also be employed. Since we all are trying to jump to the top of Mt. Everest overnight, the available resources may not be enough. Ultimately we point out our fingers towards politicians and say he/she is corrupted; s/he is useless, they are uneducated; they don't listen to the educated folks, so on and so forth. The country should have enough production and people should be productive, then only leaders can give enough monies!!! Isn't it?
Barring few ocassions (very rarely), have you ever seen doctors, engineers, professors, corporate executives lawyers coming out to the street and protesting againt the misdeed of the government? Isn't it their responsiblitiy to teach common folks, who are mostly uneducated (due to lack of opportunities) how to protest in decent ways? These common folks are doing in the same way whatever they learnt. But we proudly say situation in Nepal is really bad; we cannot go back to Nepal; we are shamed of being Nepali, Nepali Janatas are bheda and many more.
Let's come back to the point.
- Who is there to scrutinize the documents/contracts? Where are the so called scholars; how many scholars and water experts have presented their atlernative views?
- Let's say, Interim Parliament doesn't have legitimate power, how long you are gonna keep the development in limbo; what do you think is the alternative way? We are educted people, we should give the clear answer. We can not blame the politicians again. If they shouldn't do that, what should they have done? Not only question, come up with answers.
- What is the alternative to dam breaks? If there are, you can give the advice.
- What should have been there in the contract in the event the principal/contractor's period is over?
I have no doubts you have raised good questions. We are expert in raising the questions, but have no solutions. Eventually we turn towards our politicians for excuse.
Last edited: 25-Jan-08 05:08 PM
|
|
|
GP
Please log in to subscribe to GP's postings.
Posted on 01-25-08 8:26
PM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
removed.
Last edited: 08-Feb-08 11:47 PM
|
|
|
CopiCat
Please log in to subscribe to CopiCat's postings.
Posted on 01-25-08 9:01
PM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
Thank you so much for the nomenclature.
I am sorry, I was not intending to offend you. If you are not satisfied with my views, you can simply discard them. I was expecting rational and sensible brainstroms but you landed with something else.
In fact, I was not thinking of utilizing internal resources (I mean adequate capital lying idle in commercial banks of Nepal and also under the carpet). Nepal does not really need FDI (Foreign Direct Investment), I understand now!!!
|
|
|
ImI
Please log in to subscribe to ImI's postings.
Posted on 01-25-08 9:13
PM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
Who says India is the sole Buyer of Nepal's electricity???Imagine a world power grid:A grid that joins whole world with energy.It is not hypothetical.With energy scarce UN should pass a resolution to share and let share the renewable energy around the world.There should be no boundaries.Which means Nepal can light South Africa.In the long run , it is beneficial to whole world.
But for the mean time,Lets invest in our community, Small community hydro projects.We do not need Big project to be energy independent.Invest in community, city, district and then whole country will have ripple effect.A independent economy.Creates local job opportunity.This is more towards socialist ideal but this is what Nepal needs right now rather than begging for big projects from which we don't even get enough cut.Utilize Nepal's resources - engineers, labors,bricks, cement etc etc..This will ensure economic prosperity from bottom up.
People are not getting it :We are not against India.Of course this is business so why would they do bad deal.We are against The fundamental principle of Begging.
GET THIS IN YOUR HEAD: IT IS NOT AGAINST INDIA .THESE POLICY ARE AGAINST NEPAL.BY BEGGING , WE WILL REMAIN POOR AND DEPENDENT NATION FOREVER.WE HAVE SEEN THIS IN PAST AND THIS WILL REMAIN.
|
|
|
Harka_Bahadur
Please log in to subscribe to Harka_Bahadur's postings.
Posted on 01-25-08 9:24
PM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
EATING GETTING NOTHING LEATHER CAP WEARING " KHAI NAPAAI CHHLAKO TOPI LAAI JASTO BHAYO AABA YO KURO CHAI"
|
|
|
CopiCat
Please log in to subscribe to CopiCat's postings.
Posted on 01-25-08 10:45
PM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
This reminded me of Hisila Yami's plan to mobilize local resources for the Melamchi Project. Ultimately, she got a sigh of relief once ADB assured of funding after Prachanda's miserable pleas.
Like you guys, I am not against the use of internal resources. Some local companies like BPC are doing very well too. No one has talked about begging and against the investment by local enterpreneurs. The matter is only of protesting the recent deal with GMR, that happens to be Indian.
Estimated hydropower potential of Nepal is about 83K MW,out of which about 43K MW is considered economically viable. Almost 25% of the total population has access to electricity now. If load shedding is to take into account, the figure comes below 15%. If the current distribution rate is to be maintained, Nepal needs additional ~$5billion (~Rs 350 bn) in investment in the next 5/7 years as per world bank estimate. Forget about the 100% access to electricity. We have already seen the dream of West Seti 750 MW project by Snowy Mountain (Australia). Who else is coming in Nepal to invest other than India given her (India's) dire need of power (about 6000MW annual increasing power need, only able to meet half of it).
Even the foolish person prefers local resources mobilization. But given the situation, our investment capacity and pathetic queue for the petrol and kerosene (even electricity is generated by using diseal roters), I don't really understand the basic principles/logic against the protest of the deal.
Thanks.
Last edited: 25-Jan-08 11:53 PM
|
|
|
ImI
Please log in to subscribe to ImI's postings.
Posted on 01-26-08 12:25
AM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
Basic Principle /logic protest for the deal? - As GP indicated Major National Interest decision shouldn't be taken which Copicat doesn't agree.We were promised CA 2 years ago now if it takes 200 years to CA still this GOVT. is not legitimate to decide.And whose Fault is it.?? For Copicat and others - Of course King!! - " The cabinet had directed the
team to renegotiate the projects, with free energy as the highest
priority for Nepal. The cabinet set 12 percent free energy from the
Upper Karnali and 21.9 percent (88 MW) free energy from the 402 MW Arun
III as base benefits for Nepal" - WHY SO WEAK NEGOTIATION ? only 12%.- Don't tell me you go negotiate now as i know you are capable of saying these kind of things. AND YOU SHOULD FIND ANSWER TO YOUR QUESTION IN YOUR OWN STATEMENT: Who else is coming in Nepal to
invest other than India given her (India's) dire need of power (about
6000MW annual increasing power need, only able to meet half of it). - Who were the other bidders ? How much who offered?Transparency required should be public.
It is not necessarily bad idea to set goals high .Get maximum but when you are poor you are poor.
|
|
|
shirish
Please log in to subscribe to shirish's postings.
Posted on 02-05-08 12:45
PM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
Here is one more
Himtal to Sell 80% Stake to GMR
The Indian company GMR Energy Ltd. has entered into a share purchase and joint venture agreement to acquire 80 percent stake of Himtal Hydro Power Co. (P) Ltd., which is implementing a 250-MW Upper Marsyangdi-2 Hydro Power project. In a filing to Bombay Stock Exchange, GMR Infrastructure, the parent company of GMR Energy, has notified that the relevant application has been submitted to the authorities of Nepal seeking their approval for the proposed joint venture and to start the feasibility study and environmental impact assessment.
Reports quoting Brindawanman Pradhananga, Chairman of Himtal, state that the project with its construction sites in Manang and Lamjung, was originally estimated to generate 125 MW which has now been increased to 250 MW after GMR showed interest in the project. The joint-venture deal between Himtal and GMR was signed during the energy convention held at Kathmandu last year. The total cost for the project at 125 MW capacity was estimated at 200 million US dollars which will go up as the capacity is now to be expanded.
Last edited: 05-Feb-08 12:46 PM
|
|
|
shirish
Please log in to subscribe to shirish's postings.
Posted on 02-05-08 12:51
PM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
सिक्टा विवाद कायमै / पाँच करोडको काम रोकियोकुमार श्रेष्ठ, (बाँके)। राज्यको आन्तरिक लगानीको सबैभन्दा ठूलो प्रोजेक्ट सिक्टा सिंचाई आयोजनाको विवादले ठूलो रूप लिँदै गएको छ। पाँच दिनदेखिको बन्दले आयोजनामा ५ करोड रुपियाँबराबरको काम रोकिइसकेको छ।
चाइनिज ठेकेदार कम्पनी सिनो-हाइड्रोका मजदुर र नेपाली मजदुरबीच सोमबार झडप भएपछि आयोजनाको काम कारबाही ठप्प भएको हो। दैनिक ७०/८० लाख रुपियाँ बराबरको काम हुने आयोजनामा पाँच दिनदेखि काम कारबाही अघि बढ्न सकेको छैन।
मजदुरहरुले राखेको ३८ बुँदे मागमध्ये तलब वृद्धिको बाहेक अन्य माग पूरा भइसकेका छन्। मजदुरहरुले अहिलेको तलबमा १७ प्रतिशतले वृद्धि हुनुपर्ने अडान राखेका छन् भने ठेकेदार कम्पनीले नेपालको श्रम कानुनअनुसारको रकम दिन तयार रहेको जनाएको छ।
शुक्रबार दलका मजदुर संगठनका प्रतिनिधि, ठेकेदार कम्पनी र मजदुरबीच भएको छलफल पनि बिनानिष्कर्ष नै टुंगिएको छ।
नेपाली मजदुरहरु १७ बाट १२ प्रतिशतमा झरेको र ठेकेदार कम्पनीले प्रतिदिन प्रतिव्यक्ति ५ रुपियाँ बढाइदिने बताए पनि सहमति हुन नसकेको आयोजनाका प्रमुख कृष्णप्रसाद तिमिल्सेनाले बताउनुभयो।
ठेकेदार कम्पनीले शुक्रबार पनि विवाद नमिलेकाले शनिबारदेखि काम थाल्ने दाबी गरेको छ। यता, नेपाली मजदुरहरुले भने कुनै पनि हालतमा काम कारबाही अगाडि बढाउन नदिने अडान राखेका छन्।
ठेकेदार कम्पनीले केही मजदुरलाई साथमा लिएर काम गर्न अगाडि आएमा र अरुको कारणले काम रोकिएमा उसले प्रतिदिन नेपाल सरकारसँग ३० लाख रुपियाँसम्म क्षतिपूर्ति माग गर्न सक्छ।
जिल्लाको ३६ गाविसको ३१ हजार हेक्टर जमिन सिंचाई हुने सिक्टाको हेडवर्क्स निर्माण भइरहेको छ। त्यहाँ ६ सय नेपाली र ४० जना चिनियाँ मजदुरले काम गरिरहेका छन्।
दैनिक भइरहेको छलफलले समस्या समाधान नभएपछि आयोजना प्रमुख तिमिल्सेना राजनीतिक दल र प्रहरी प्रशासनलाई गुहार गर्ने सोचमा पुग्नुभएको छ।
ँठेकेदार कम्पनीले आफ्ना ४० जना चिनियाँ र केही नेपाली कामदारलाई लिएर काम गर्न गयो र हामीले त्यसको वातावरण बनाउन सकेनौं भने उसले क्षतिपूर्ति दाबी गर्न सक्छ’, आयोजना प्रमुख तिमिल्सेनाले भन्नुभयो- ँकाम नगरीकनै ठेकेदार कम्पनीलाई दैनिक ३० लाखसम्म राज्यले दिनुपर्यो भने हाम्रो हालत के होला ?’
|
|
|
shirish
Please log in to subscribe to shirish's postings.
Posted on 02-11-08 9:41
PM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
India positive on providing Nepal 40 MW
Request for another 20 MW from Tanakpur
POST REPORT
KATHMANDU, Feb 12 - India's Ministry of Power is positive on providing Nepal 40 megawatt (MW) of electricity, which Nepal Electricity Authority (NEA) is looking to import from the Duhabi-Kataiya transmission link, NEA's Managing Director Arjun Kumar Karki said on Monday.
After India's leading power trader PTC India Ltd told Nepal last month that it would be able to provide the northern neighbor only 15 MW of the 40 MW India had promised last
year, effort was initiated at the government level to procure power.
"Indian government is ready to provide us the full forty megawatts," Karki told parliament's Finance Committee. "We can import power from Duhabi-Kataiya transmission link," he said. Nepal is already importing 50 MW from the link based on the power exchange agreement between the two countries. Still, consumers are facing up to eight hours of daily power cuts.
On Monday, NEA also wrote to PTC India Ltd requesting it to supply 20 MW of additional power from Tanakpur.
"We have found that it is technically feasible to import an additional twenty megawatts from Tanakpur," Karki said.
House panel for customs waiver on CFLs
Lawmaker and Former Finance Minister Bharat Mohan Adhikari, who chaired the House panel meeting on Monday, told NEA that the panel would ask the Ministry of Finance to waive off customs on import of Compact Fluorescent Lamps (CFLs), which use only a quarter of the power used by traditional light bulbs to provide the same degree of illumination.
"We will ask the ministry to waive off customs for CFLs and also to provide a revolving fund to NEA to make consumers switch from traditional lighting bulbs to CFLs," said Adhikari.
For demand management, NEA is immediately starting distribution of leaflets to consumers, through its billing staff, explaining the benefits of CFLs as well as a scheme to allow consumers to switch to CFLs with zero initial investment.
NEA has proposed that it be provided a revolving fund of Rs 500 million so that it can buy CFLs, install them in people's homes for free, and pay CFL suppliers in installments from consumers' bills. Switching to CFLs will reduce electricity consumption of individual households. NEA will continue to charge consumers an average of their past electricity bills for as long as the margin between their past bills and actual consumption do not pay back all the installments of CFL.
The NEA has also asked the house panel to raise customs on power inefficient inverters, make it mandatory for factories not to operate during peak hours, and to expand the adoption of CFLs in government offices and street lamps.
Proposal to supply 250 MW to Nepal
As a longer-term solution to Nepal's power crisis, India's Infrastructure Leasing and Financial Services (IL&FS), which is partnering with NEA to build four high-voltage transmission highways across the Nepal-India border, recently proposed to NEA to supply up to 250 MW to Nepal from a 500 MW thermal plant it is setting up in India, Karki told the house panel.
"I Think this is a workable proposal," said Karki.
However, the arrangement will come into effect only by 2010 end as it will take three years to set up the plant.
IL&FS has proposed to supply power at IRs 2 to IRs 2.50 per unit.
According to NEA's forecast, the country will face progressively worse power cuts for at least the next five years, after which projects in the pipeline are expected to start plugging the demand-supply gap.
|
|
|
shirish
Please log in to subscribe to shirish's postings.
Posted on 02-13-08 12:20
PM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
from SpotlightKARNALI PEOPLE ROBBED OF VAST WATER WEALTH Suicidal Upper Karnali Hydropower Deal AB Thapa
Several dailies including THE KATHMANDU POST of January 25, 2008 reported horrifying news that the Ministry of Water Resources has signed a MoU with a GMR team to finalize the deal to allow latter to implement the 300 MW Upper Karnali Project. The MoU to implement the 300 MW Upper Karnali Hydropower is going to be a suicidal deal. The Karnali people will be robbed of the great opportunity to benefit from their vast water wealth as a result of the decision to implement the 300 MW Upper Karnali project. The proposed 300 MW Upper Karnali project can be implemented only at the cost of sacrificing the 4180 MW Upper Karnali Storage project According to the pre-feasibility study report the 300 MW Upper Karnali project and the 4180 MW Upper Karnali storage project are mutually exclusive. The 4180 MW Upper Karnali project is the most attractive hydropower among the projects identified so far in Nepal. It far excels even the highly attractive 10,800 MW Karnali Chisapani project in performance to generate electricity at extremely low cost on a massive scale. It can be roughly said that the 4180 MW Upper Karnali project might be able to produce as much as 50% of the total energy generated by the 10,800 MW Karnali Chisapani project at only about 1/3 cost of the latter. The overwhelming superiority of the 4180 MW Upper Karnali storage project among the large hydropower projects identified so far in Nepal is so obvious that the team of the consultants conducting the pre-feasibility study of the 300 MW Upper Karnali project under the financial assistance of the World Bank found themselves duty bound to warn us to refrain from harming the 4180 MW Upper Karnali storage project. They have clearly stated in the pre-feasibility report that the construction of the 300 MW Upper Karnali project will preclude the implementation of the 4180 MW Upper Karnali storage project. Is Parliamentary Committee Adequately Informed? It is reported in the newspaper that at some stage the Parliamentary Natural Resources and Means Committee was also involved. It is not clear whether or not the Parliamentary Committee was informed about the fact that the 300 MW Upper Karnali project and the mammoth 4180 MW Upper Karnali storage project are mutually exclusive. Do all the members of the Parliamentary Committee know the whole truth about the Upper Karnali projects? Is the Acharya task force or another Committee under the former finance secretary, set up to advise the Government, competent to make satisfactory recommendation, which requires in-depth analysis of all relevant technical documents? . People Must be Informed There is no escaping the fact it is not possible to implement the proposed 300 MW Upper Karnali project without sacrificing the most attractive 4180 MW Upper Karnali storage project. Do not the people of our country have the right to know from the Water Resources Ministry and Parliamentary Natural Resources and Means Committee why the mammoth 4180 MW Upper Karnali storage project is being sacrificed to implement the relatively tiny 300 Upper Karnali project? Why Upper Karnali Storage So Attractive The Karnali river makes a big loop in its lower reach near a place called Asare. From here the river flows in the south-east direction for about 25 kilometers, after that the river makes a complete reversal in its direction. The river comes back to a point just two kilometers away from its earlier position near Asare. There is a drop of about 150 meters in Karnali river bed elevations between these two positions merely two kilometers away from one another The project to utilize this bend for power generation is known as the Upper Karnali Project. . There are very good sites to build a large storage dam at the beginning of the bend. Thus, it makes the Upper Karnali Storage Project far superior to the 10,800 MW Karnali Chisapani Project in terms of per unit capacity investment cost because its hydropower station would be operating at a firm head two times greater than that of the latter though the total length of the waterway of both these hydropower plants would be almost exactly the same. Large Cost Reduction at Higher Heads Of all the site characteristics, head is the most important. Design guidelines, 1989 approved by the American Society of Civil Engineers ( a document used throughout the world for the design of hydropower) has given some simple reasoning that would help to explain why the Upper Karnali project operating at a head about two times greater by comparison with the Chisapani hydropower could be built at far less per unit installed capacity cost. "Very simply if one doubles the head the quantity of water needed to produce a certain amount of energy is halved, Thus, for like site energy development the conduit area and reservoir volume are halved and further large cost reductions occur for powerhouse and machinery costs. This fundamental consideration is at the root of the large cost reductions that occur at higher heads." Needless to mention that the lower investment cost means the generation cost of the electricity would also be less. Comparative Investment Cost of Upper Karnali Storage By comparison with the mammoth 10,800 MW Karnali Chisapani Project the firm head of the Upper Karnali Storage Project would be almost two times greater. It can be derived based on Stage A Optimization Study Data of the World Bank financed Karnali Project (Chisapani) Study report that per KW installed capacity construction cost of the Upper Karnali Storage Project could be only about 2/3 of such cost of the project at Chisapani. If such comparative cost reduction advantage is treated as additional bonus to accrue to Nepal on top of normal royalty to be received from private developer then our country might be able to earn per year at present cost of peaking energy about US $ 300 million as extra bonus which is equivalent to gross value of the total annual production of paddy in the whole country considered to be between 2.5 to 3 million tons at a price of about US $ 100 per ton. Upper Karnali Pre-feasibility Report The World Bank supported pre-feasibility study has clearly explained that the 4180 MW Upper Karnali Storage Project and the 300 MW Upper Karnali Diversion Project are mutually exclusive. The relevant excerpt from the World Bank supported study report is presented below. “Even when assuming that the KR 1 A run-of-river project (it indicates the small 300 MW Upper Karnali project) is a sunk cost, it will be seen that a single large power plant (4180 MW) associated with the major storage project is less costly than the combined cost of smaller plant at the same location (3532 MW) and a second power plant at the foot of the storage dam ( 348 MW) discharging directly into the KR 1A run-of-river project head pond. Based on this assessment, it appears that the later development of the major hydro storage project at Site KR 1 ( 4180 MW Upper Karnali Storage Project) would cause the KR 1A run-of-river project to be effectively discontinued. There may be limited opportunity for secondary energy generation during the periods of spillageâ€. Foreign Expert Against 300 MW Upper Karnali Mr. Paul Terrell from the Bechtel International of the USA was Chief Advisor Consultant of the Upper Karnali Project study conducted under the World Bank financial assistance. Mr. Paul Terrell has categorically cautioned Nepal in his article published in the journal “HIMAL†that our country should never compromise optimum development for the sake of a quick deal. In Conclusion Our grandiose national plans to develop our water resources to uplift the economic condition of our country in general and the people of Karnali in particular would be nothing more than an empty rhetoric if we failed to intervene in time to save the 4180 MW Upper Karnali Storage Project which might be the best even in the whole world for the generation of cheap peaking energy on a large scale. We should not hesitate to invite competent foreign experts for advice if we find ourselves not capable to make correct judgment on this very important matter.
|
|
|
aman
Please log in to subscribe to aman's postings.
Posted on 02-24-08 11:52
AM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
Since India is major power purchaser it is good for Nepal if Indian companies get first priority in competetively. Who cares who gets project. Nepal urgently need projects else Nepal will be History with ongoing economic situation. Khali Dimag saitan Ka ghar. why so many people show up in political demonstrations coz they are unemployed.
|
|
|
shirish
Please log in to subscribe to shirish's postings.
Posted on 03-03-08 6:49
PM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
अरुण-३ बनाउन सम्झौता
बलराम बानिया“/विकास थापा
काठमाडौं, फागुन १९ - भारतीय सरकारी कम्पनी सतलज जलविद्युत् निगमले ४०२ मेगावाट क्षमताको संखुवासभामा पर्ने बहुचर्चित अरुण-३ जलविद्युत् आयोजना निर्माण गर्ने भएको छ ।
सरकार र सतलजबीच आइतबार अरुण-३ आयोजना निर्माणसम्बन्धी सम्झौता -एमओयू) भएको छ । समझदारीपत्रमा जलस्रोत मन्त्रालयका सहसचिव अनुपकुमार उपाध्याय र सतलजका डेपुटी म्यानेजर सञ्जय उप्पलले हस्ताक्षर गरेका छन् ।
विश्व बैंकको ऋण सहयोगमा २०५२ सालमा विद्युत् प्राधिकरणद्वारा नै निर्माणका लागि ठेक्कासमेत भइसकेको यो आयोजना 'मह“गो' भन्दै विरोध भएपछि रद्द भएको थियो ।
जलस्रँेत मन्त्रालयले सतलजसित एक महिना लामो छलफल र बहसपछि आयोजनाको टुंगो लगाएको हो । सम्झौताअनुसार सतलजले अरुण-३ बाट उत्पादित कुल विद्युतको २१ दशमलव ९ प्रतिशत -८८ मेगावाट) नेपाललाई निःशुल्क रूपमा उपलब्ध
गराउनेछ । त्यसरी प्राप्त हुने बिजुली विद्युत् बिक्रीबाट प्राप्त हुने रोयल्टी र निर्यात करको अतिरिक्त हो । विद्युत् नीति-२०५८ अनुसार सतलजले आपmनो कुल आम्दानीको ७ दशमलव ५ प्रतिशत सरकारलाई रोयल्टीबापत बुझाउनुपर्नेछ । त्यसबाहेक सरकारले शून्य दशमलव शून्यशून्य ५ प्रतिशत निर्यात कर पाउनेछ ।
अरुणबाट वषर्ायाममा करिब २ अर्ब ९० करोड तथा हिउ“दयाममा एक अर्ब ५५ करोड युनिट बिजुली उत्पादन हुने अध्ययनले देखाएको
छ । यसको लागत ८६ करोड अमेरिकी डलर -हालको मूल्यमा ५४ अर्ब १८ करोड रुपैया“) पर्छ ।
यसबाट उत्पादित बिजुली करिब १२५ किलोमिटर लामो ४४० केभीको उच्च क्ष्ँमतामा दुहबीसम्म विस्तार गरिने योजना छ । सतलजले आयोजना प्रवेश मार्गको स्तरोन्नति गर्ने र बा“की सडक निर्माण गर्नेछ । यो आयोजनासम्म पुग्न अझै ६४ किलोमिटर सडक बनाउन बा“की छ ।
सम्झौता अनुसार सरकारले अरुण-३ बाट जडित क्ष्ँमता र ऊर्जा दुवैमा निःशुल्क बिजुली पाउनेछ । मन्त्रालयद्वारा जारी विज्ञप्तिका अनुसार उसले विद्युत् उत्पादन सुरु भएको मितिदेखि बिजुली दिनुपर्नेछ । उक्त कम्पनीले नेपालले सहजै प्राप्त गर्ने गरी विद्युत् प्रसारण लाइनको उपयुक्त स्थानबाट बिजुली उपलब्ध गराउनुपर्नेछ ।
सतलजस“गको वार्ता टोलीका संयोजक तथा सहसचिव उपाध्यायका अनुसार अरुण-३ बाट सरकारले चाहेमा जति पनि बिजुली किन्न पाउने सम्झौता छ । 'हाम्रँे माग पूरा गरेपछि मात्र उसले भारतमा बेच्न पाउ“छ,' सम्झौतापछि उपाध्यायले कान्तिपुरसित भने ।
सरकारले अरुण-३ आयोजना निर्माण, सञ्चालन र हस्तान्तरण
-बुट) अवधारणाअनुसार ३० वर्षा लागि प्रदान गर्न लागेको हो । निर्माण सुरु गरेको ३० वर्षछि सतलजले अरुण तेस्रो आयोजनाको स्वामित्व चालू हालतमा सरकारलाई हस्तान्तरण गर्नुपर्नेछ ।
सम्झौताअनुसार कम्पनीले प्रतिमेगावाट एक लाखका दरले ४ करोड २ लाख रुपैया“ तिरेर सरकारबाट र्सर्वेक्षण अनुमतिपत्र प्राप्त गर्नेछ । र्सर्वेक्षण सकिएपछि सतलजले प्रतिमेगावट ५ लाखका दरले २० करोड १० लाख रुपैया“ बुझाई सरकारबाट विद्युत् उत्पादन अनुमतिपत्र प्राप्त गर्नेछ ।
सतलजले सरकारस“ग समझदारी गरेको चार महिनाभित्र आयोजनाको र्सवेक्षण अनुमतिपत्र लिइसक्नर्ुपर्ने उपाध्यायले बताए । आयोजना निर्माणका लागि सतलजले वित्तीय स्रोत जुटाएको ६० महिनाभित्र अरुण-३ को निर्माण कार्य
सम्पन्न गर्नेछ ।
उक्त कम्पनीले अरुण-३ आयोजनाको अध्ययनका लागि यसअघि खर्च भएको सरकारको ४५ करोड १४ लाख रुपैया“ नेपाललाई बुझाउने सहमतिसमेत गरेको छ ।
उपाध्यायका अनुसार सम्झौतामा उल्लिखित 'तोकिएको समयमा तोकिएको काम सम्पन्न नगरे' धरौटी जफत गरी लाइसेन्स खारेज हुने प्रँवधान छ । निर्माण नगरी लाइसेन्समात्र ओगटेर बस्न नदिन यस्तो प्रँवधान राखिएको हो । 'उसले छ/छ महिनामा प्रगति विवरण बुझाउनर्ुपर्नेछ,' उपाध्यायले भने । जनआन्दोलन-०६२/६३ को उपलब्धि स्वरूप गठित सरकारले अरुण-३ सहित माथिल्लो कर्ण्ााली
-३०० मेगावाट) र बूढीगण्डकी
-६०० मेगावाट) मा विश्वव्यापी प्रतिस्पर्धा गराएको थियो । कर्ण्ाालीमा १४ र अरुणमा ९ कम्पनीले प्रतिस्पर्धा गरेका थिए ।
सरकारले प्रतिस्पर्धा गराउ“दा प्रमुख र्सत निःशुल्क बढी बिजुली राखेको थियो । प्रतिस्पर्धामा सामेल हु“दा सतलजले नेपाल सरकारलाई ४ दशमलव ५ प्रतिशत मात्र ऊर्जा दिने प्रस्ताव गरेको थियो ।
प्रतिस्पर्धामा परेका प्रस्तावउपर मूल्यांकन गरी सरकारलाई सुझाव दिन पर्ूव अर्थसचिव भानुप्रसाद आचार्यको संयोजकत्वमा गठित कार्यदलले सतलजलाई दोस्रँे नम्बरमा सिफारिस गरेको थियो । पहिलो नम्बरमा भारतकै अर्कै कम्पनी जीएमआर थियो । भानु कार्यदलले माथिल्लो कर्ण्ाालीको पहिलो नम्बरमा पनि जीएमआरलाई नै राखेको थियो ।
अन्तरिम संसदको प्रँकृतिक स्रँेत तथा साधन समितिले दुइटै आयोजना एउटै कम्पनीलाई नदिन र बढी ऊर्जा दिनेलाई आयोजनाको लाइसेन्स दिन निर्देशन दिएपछि सरकारले प्रस्तावक कम्पनीहरूस“ग प्राथमिकताक्रम अनुसार वार्ता सुरु गरेको हो ।
यसअघि सरकारले माथिल्लो कर्ण्ााली जीएमआरलाई दिने निर्ण्र्ाागरिसकेको छ । जीएमआरले माथिल्लो कर्ण्ाालीबाट नेपाललाई निःशुल्क रूपमा १२ प्रतिशत बिजुली र सित्तैमा २७ प्रतिशत सेयर दिने सम्झौता गरेको छ ।
गत मंसिर १६ गतेको मन्त्रिपरिषद्ले अरुण-३ र माथिल्लो कर्ण्ाालीसम्बन्धी टुंगो लगाउने अख्तियारी जलस्रँेत मन्त्रालयलाई दिएको थियो । मन्त्रालयले संसदीय समितिको निर्देशन पालना हुने गरी प्रस्तावक कम्पनीहरूस“ग वार्ता गर्न सहसचिव उपाध्यायको संयोजकत्वमा समिति गठन गरेको थियो । अरुण-३ भारतीय कम्पनीलाई निर्माण गर्न दिइएको दोस्रो हो । माघ १० गते सरकारले माथिल्लो कर्ण्ााली निर्माण गर्न दिन अर्को भारतीय कम्पनी जीएमआरसित समझदारी गरिसकेको छ ।
जीएमआरले माथिल्लो कर्ण्ाालीमा सरकारलाई सित्तैमा २७ प्रतिशत सेयर दिने सहमति गरेको छ । तर सतलजले अरुण-३ मा त्यस्तो निःशुल्क सेयर भने नदिने भएको
छ । स्रोतका अनुसार सतलजले अरुण-३ मा जीएमआरले माथिल्लो कर्ण्ाालीमा दिनेभन्दा झन्डै दोब्बर बढी बिजुली सित्तैमा दिने भएकाले सेयर नदिएको हो ।
सरकारले ती दर्ुइ आयोजनाबारे निर्ण्र्ाागर्न जलस्रोत मन्त्रालयले सहसचिव उपाध्यायको संयोजकत्वमा जल तथा शक्ति आयोगको सचिवालयका सहसचिव राजेन्द्रकिशोर क्षत्री, विद्युत् विकास विभागका उपमहानिर्देशक सुनिलबहादुर मल्ल र विद्युत् प्राधिकरणका उपकार्यकारी निर्देशक उत्तरकुमार श्रेष्ठ रहेको वार्ता समिति गठन गरेको थियो ।
|
|
|
harikancha
Please log in to subscribe to harikancha's postings.
Posted on 03-03-08 7:05
PM
Reply
[Subscribe]
|
Login in to Rate this Post:
0
?
|
|
Came to hear that india made tarai forum to have agreement with govt as an exchange for providing hydropower for indian companies.
|
|